The new building at the Geberit plant in Lichtenstein (DE) is now occupied. A new production line is used to manufacture Duofix frames. And a new Plant Manager marks the beginning of a new era.

The diggers start work at the Geberit plant in Lichtenstein in spring 2022. Two years later, and the building extension is occupied. This mammoth project not only increases production space, but also brings a host of other possibilities with a wing for administration, sales and a company restaurant.

New line

From January 2025 onwards, the blue Duofix frames will be manufactured on a new production line in the new building. The line is special in many ways: at just over 180 metres, it is the longest continuous production line at Geberit. Measuring just over 74 metres in length, the largest element is the powder coating plant that gives the frame its blue colour. The entire plant is fully automated. “The product is manufactured without anyone laying a finger on it,” says the new Plant Manager Michiel Willi.

A seamless handover: the former Plant Manager Thomas Schweikart is retiring, and his successor Michiel Willi has already taken over.
A seamless handover: the former Plant Manager Thomas Schweikart is retiring, and his successor Michiel Willi has already taken over.
The new production line is 180 metres long, with just over 74 metres taken up by the powder coating plant shown here.
The new production line is 180 metres long, with just over 74 metres taken up by the powder coating plant shown here.
The iconic blue Geberit Duofix frames are produced in Lichtenstein.
The iconic blue Geberit Duofix frames are produced in Lichtenstein.

The product is manufactured without anyone laying a finger on it.

Michiel Willi, Plant Manager in Lichtenstein

Change at the top

At the same time, it is the end of an era: Lichtenstein’s Plant Manager Thomas Schweikart is retiring and handing over the reins to Michiel Willi. The handover is going seamlessly: Michiel Willi joins the Geberit plant in Lichtenstein just over four years ago after already working in Shanghai and the German plants in Langenfeld and Wesel. The initial situation couldn’t be better. With a new building, new line and new boss, the highly motivated team from Lichtenstein can look to the future with confidence.